Manufacturing Facilities

Merit Medical

Location: South Jordan, Utah

Project Owner / Client: Merit Medical

General Contractor: Jacobsen Construction

Architect: MHTN Architects

Mechanical Engineer: Colvin Engineering

Mechanical Contractor: CCI Mechanical, Inc.

CCI Mechanical Role: Heating, Ventilating, Air Conditioning, Temperature Controls, and Plumbing

Building Highlights: 180,000 ft.² - Total (2 floors) 48,000 ft.² - Electrical Building 60,000 ft.² - Class 100,000 Clean Room 5,000 ft.² - Class 10,000 Clean Room Mechanical Systems: Two (2) Chillers - 250 Tons Each Four (4) Boilers Ten (10) Pumps Nine (9) Air Handlers Thirty (30) VAV Boxes

Sweet Candy Company

Location: Salt Lake City, Utah

Project Owner / Client: Sweet Candy Company

General Contractor: Layton Construction Co., Inc.

Architect: Case, Lowe & Hart

Mechanical Engineer: Case, Lowe & Hart

Mechanical Contractor: CCI Mechanical, Inc.

CCI Mechanical Role: Heating, Ventilation, Air Conditioning, and Plumbing

Building Highlights: Office / Warehouse - 180,000 ft.² Office - 18,000 ft.² Warehouse - 50,000 ft.² Production - 112,000 ft.² Mechanical Systems: Two (2) 300 HP High Pressure Steam Boilers One (1) 50 HP High Pressure Steam Boiler One (1) Deaerator Complete Steam and Condensate Piping System Two (2) 255-Ton Water Cooled Chillers One (1) Cooling Tower Complete Chilled Water Piping System Twelve (12) Haakon Roof-Mounted Air Handling Units Four (4) Constant Volume Rooftop (Cooling Only) Units One (1) VAV Rooftop Unit Thirty-Four (34) Exhaust Fans Two (2) Heat Exchangers with Complete Heating Hot Water Piping System Fabric Duct Sock Distribution System Two (2) Steam Hot Water Heaters with Complete Hot Water Washdown System One (1) Duplex Water Softener One Hundred Twenty-One (121) Plumbing Fixtures Sixty-Nine (69) Floor Drains/ Twenty-Seven(27) Floor Sinks/ Thirty (30) Roof Drains Three (3) Air Compressors Two Thousand Nine Hundred Feet (2,900') of 4" Compressed Air Piping

Quartzdyne

Location: West Valley City, Utah

Project Owner / Client: Argent Group

General Contractor: Layton Construction Co., Inc.

Architect: MHTN Architects

Mechanical Engineer: CCI Mechanical, Inc.

Mechanical Contractor: CCI Mechanical, Inc.

CCI Mechanical Role: Engineering, Heating, Ventilation, Air Conditioning, Temperature Controls, and Plumbing

Building Highlights: LEED Silver (Pending) Office Area - 15,000 ft.² Manufacturing Area - 20,700 ft.² Class 10,000 Clean Room Area - Room 1 = 3,920 ft.² / Room 2 = 1,800 ft.² Mechanical Systems: One (1) 300-Ton Chiller Two (2) 94% High Efficiency Boilers Four (4) VAV Rooftop Units Two (2) Constant Volume Units for Clean Rooms One (1) Liebert Unit for Server Room One Hundred One (101) Hepa Diffusers Twenty-One (21) Exhaust Fans Low Flow Plumbing Fixtures