Location: Salt Lake City, UT
Project Owner / Client: Questar
General Contractor: Questar
Architect: Carpenter and Stringham
Mechanical Engineer: CCI Mechanical, Inc.
Mechanical Contractor: CCI Mechanical, Inc.
CCI Mechanical Role: Total Energy Plant
Building Highlights: Independent electric generation to provide for all electrical, heating, and cooling requirements of the Questar Corporate Service Center. Mechanical Systems: Three (3) 430 KW Natural Gas Turbines Three (3) Waste Heat Boilers Three (3) 450 Ton Absorption Chillers