Location: Riverdale, UT
Project Owner / Client: America First Credit Union
General Contractor: Okland Construction Co., Inc.
Architect: DMJM
Mechanical Engineer: Bruns-Pak
Mechanical Contractor: CCI Mechanical, Inc.
CCI Mechanical Role: Heating, Ventilation, Air Conditioning, Plumbing, Piping and Temperature Controls
Building Highlights: Seismically Base Isolated Structure for Secure Data Center. Total Building - 37,000 ft.². Construction Schedule: Start - September 2003 / Completion - April 2004. Mechanical Systems: Ten (10) Computer Room Units w/260 of Cooling Capacity. Ten (10) Dry Coolers Serving Computer Room Units. Three (3 Rooftop Units w/Seismic Isolation and 42 Tons of Cooling Capacity. One (1) Heat Recovery Unit. Twelve (12) Electric Unit Heaters w/50 KW Heating. Complete Welded and Seismic Isolated Glycol Piping System. Complete Installation of Fuel Oil System for Emergency Generators with Control and Alarm System. Fifteen (15) Variable and Constant Volume Boxes. Sixteen (16) Exhaust, Transfer, and Supply Fans. Complete Seismic Isolated Domestic Plumbing and Piping including Seismic Swing Joins for all Piping and Plumbing Connections to Outside of Building.
Location: Salt Lake City, Utah
Project Owner / Client: Intel Corporation
General Contractor: Layton Construction Co., Inc.
Architect: Intel Corporation
Mechanical Engineer: CCI Mechanical, Inc.
Mechanical Contractor: CCI Mechanical, Inc.
CCI Mechanical Role: Engineering, Heating, Ventilating, Air Conditioning, and Plumbing
Building Highlights: Level 1 Tenant Finish - 18,000 ft.². Construction Schedule: Start - May 2000 / Completion: August 2000. Mechanical Systems: Low Pressure Duct Distribution Throughout - Utilizing Existing Capacities, Sixty (60) Anemostat Double Deflection Diffusers, Computer Room Split System, Condensate Drain System.
Location: West Jordan, UT
Project Owner / Client: Oracle
General Contractor: Holder Construction Company
Architect: Gensler
Mechanical Engineer: Syska Hennessy Group
Mechanical Contractor: CCI Mechanical, Inc. / Hill Mechanical Group
CCI Mechanical Role: Heating, Ventilating, Air Conditioning, and Plumbing
Building Highlights: Building Highlights: Total - 235,000 ft.² - One (1) Level Building - Includes 30,000 ft.² Data Center. Construction Schedule: - Start: April 2010 - Completion: December 2010. Mechanical Systems: Four (4) water cooled chillers - 10,000 tons cooling each / Four (4) cooling towers / Twenty-six (26) custom built air handling units / Two (2) VAV rooftop packaged units / One (1) constant volume rooftop packaged unit / Thirty-one (31) exhaust fans / Two (2) gas fired boilers / Soft water system / Chemical feed system.